New RotorClear RBC Package Plant For Pebble Rock Golf Estate

plant Requirements
• 440 m3/ day Domestic sewage
• The process had to be stable with minimal operator input
• Plant needed excellent turn down capabilities to cater for gradual take-up of the stands on the development
• Treated water would need to be recycled for irrigation of the golf course
• Plant was required to be low noise and low environmental impact and low energy requirement
• The plant was required to have low sludge production and for the sludge to be treated off site
plant Supplied



• The plant supplied conforms to all of the selection parameters.
• The plant utilizes the proven and very stable twin compartment anaerobic digester with Rotating Biological Contactor, Imhoff type humus Clarifier
•
The electrical control gear includes an SMS unit which notifies key personnel of any fault condition immediately • The
gearbox is generously sized and can
handle restarts from power outages
• The new media is arranged in
replaceable modules such that individual modules can be replaced without replacing the entire media pack